The guide describes upgrading the Work.AI platform from v10.3.3 to v10.3.3.1.

Prerequisites​

  • You have Work.AI up and running.
  • All Business Processes are stopped.
info

Remember to run the commands as APPLICATION_USER.

Upgrade​

To apply the patch, do the following:

  1. On the Master1 server, download the patch package and extract it into the directory with the existing installer. Make sure to follow the same directory structure as in the example below when downloading and extracting the patch package:

    cd /opt/workfusion/wf_installer/
    mkdir -pv ./patches
    cd ./patches/
    curl -k -o 'patch_10.3.3.1.tar.gz' 'https://DOWNLOAD_LINK'
    tar xzf patch_10.3.3.1.tar.gz

    A new directory named patch_10.3.3.1 with the patch content appears.

  2. Navigate to the directory with the patch content and run the command to apply the patch as in the example below:

    export ANSIBLE_PRIVATE_KEY_FILE="/PATH/TO/SSH-PRIVATE-KEY" && export ANSIBLE_VAULT_PASS='YOUR_ANSIBLE_VAULT_PASS'
    cd ./patch_10.3.3.1
    ./patch_10.3.3.1.sh apply

    The procedure takes approximately ten minutes.

info

If you are applying the patch to an environment provisioned in a multi-node setup, upload the patch package to all Master servers (in HA mode, there are three). Then, specify the additional arguments for the multi-node setup, as shown in the following example:

./patch_10.3.3.1.sh apply -c local --limit master[0]  # When applying for Master1 server
./patch_10.3.3.1.sh apply -c local --limit master[1] # When applying for Master2 server (in HA mode)
./patch_10.3.3.1.sh apply -c local --limit master[2] # When applying for Master3 server (in HA mode)